← Engineering projectsProject 01 / 10
Automation & technology development

Test-shop automation feasibility

Led the Wolverhampton test-shop automation study, mapping manual activities and decision points, evaluating existing BOC experience and defining the initial technical requirements. Established supplier input for the next investment decision.

Responsibility
Feasibility lead
Context
Wolverhampton · Reliability & Maintenance Improvement · 2025–2026
£150k–£200kestimated productivity opportunity
Results and scope
Engineering project index
Engineering approach

Mapped the manual process before defining the automation requirements, using operating experience from BOC Australia and the Global team to assess transferability.

01 / Objective

Objective and context

Assess the opportunity to automate test-shop activities and translate the existing workflow into requirements suitable for technical and contractor review. The assessment connected technician activity, process interfaces, operational constraints and the potential productivity benefit.

02 / Contribution

Technical contribution

  1. Process and activity mapping

    Mapped manual work, technician interventions and decision points to establish the operating requirements an automated system would need to address.

  2. Technology review

    Assessed BOC Australia and Global experience to inform the UK study. Considered the relationship between the established operating process and the proposed automation approach.

  3. User requirements specification

    Produced a team-approved initial user requirements specification, translating the feasibility work into a basis for technical discussion and contractor assessment.

  4. Contractor engagement

    Identified three potential contractors and coordinated site surveys. Two surveys were completed at the recorded review point, providing supplier input for subsequent development.

03 / Results

Results and scope

Identified an estimated £150,000–£200,000 productivity opportunity. Delivered an approved initial requirements specification, a shortlist of potential contractors and completed site-survey input for the next investment decision.

Scope of responsibility and evidence

Feasibility and requirements development. The productivity figure is an estimate of the identified opportunity, not a realised saving.

Tools and methods

  • Process mapping
  • User requirements specification
  • Technology assessment
  • Contractor coordination
  • Productivity assessment
Professional enquiries

Contact Kevin Muleya