Asset risk, investment and cost control
Led annual Condition and Risk Assessment reviews to 100% completion at Motherwell and Grangemouth. Developed 2025/26 maintenance, overhaul and replacement priorities with the plant manager and negotiated a contractor charge reduction after a scope shortfall.
Engineering project index
Used asset condition, lifecycle risk and cost together when developing priorities. Addressed the contractor scope shortfall through a negotiated charge reduction.
Objective and context
Translate asset condition and lifecycle risk into practical maintenance and investment priorities, while reviewing contractor charges against the delivered scope.
Technical contribution
Condition and risk reviews
Led the annual Condition and Risk Assessment reviews at both sites to 100% completion.
Maintenance and investment priorities
Developed 2025/26 maintenance, overhaul and replacement priorities with the plant manager, balancing condition, lifecycle risk and cost.
Commercial resolution
Negotiated a contractor charge from £8,000 to £2,400 following a scope shortfall, securing a £5,600 reduction.
Results and scope
Completed the annual reviews at both sites, informed the following year’s maintenance and replacement priorities and reduced the disputed contractor charge by £5,600.
The £5,600 figure is the reduction in the contractor charge. It is separate from the £7,000 Crawley reliability saving.