High-pressure analysis-hose reliability
Led the investigation into recurring high-pressure analysis-hose failures at Crawley. Connected technician handling and bending with failure evidence, developed two options and secured technical-authority agreement on a revised hose.
Engineering project index
Identified bending during technician handling as a contributing factor and incorporated the equipment–operator interaction into the option assessment.
Objective and context
Investigate premature hose failure by examining the component, handling practice and operating conditions together. The work required a practical change supported by failure evidence and technical review.
Technical contribution
Failure investigation
Observed technician handling alongside the available failure evidence. Examined bending and its relationship to the repeated failures.
Option development
Developed two technical options and reviewed the proposed change with the technical authority. Secured agreement on a revised hose suited to the operating application.
Implementation and follow-up
Monitored installation and reviewed the replacement in use. Used the follow-up period to check the result rather than treating component replacement as the end of the investigation.
Results and scope
Business Analytics verified a £7,000 saving. No further failure was reported at the recorded review point.
The reliability observation relates to the recorded follow-up period. Financial verification is attributed to Business Analytics.