← Engineering projectsProject 05 / 10
Engineering execution & operating controls

Engineering change and site operations

Progressed engineering-change actions across Motherwell and Grangemouth and chaired monthly reviews for six months. Coordinated technical, contractor and documentation actions alongside improvements to operating information and site controls.

Responsibility
Graduate Operations Engineer
Context
Motherwell & Grangemouth · Sep 2024–Aug 2025
~30engineering changes progressed across two sites
Results and scope
Engineering project index
Engineering approach

Used regular change reviews to coordinate technical actions and dependencies, supported by site information and contractor-control checks.

01 / Objective

Objective and context

Progress controlled engineering change within live air-separation operations. Technical actions, contractor controls, equipment interfaces and documentation needed to remain aligned through delivery and close-out.

02 / Contribution

Technical contribution

  1. Change coordination

    Progressed actions across approximately 30 engineering changes and chaired monthly reviews for six months. Workstreams included equipment interfaces, cooling towers, cryogenic vessel service changes and pump insulation.

  2. Technical and contractor actions

    Coordinated technical, contractor and documentation actions, including RAMS, P&ID updates and written-scheme actions. Checked turnaround contractor controls and supported a causal-tree investigation into contractor RAMS non-compliance.

  3. Operating information

    Improved Historian mimics with site and remote-operations teams and analysed process-safety indicator trends. Connected process information with a clearer view of plant operation.

  4. Work coordination

    Developed a Work Assignment Tool with the plant manager to support the allocation and coordination of site work.

03 / Results

Results and scope

Progressed engineering-change actions across two operating sites, maintained a regular review process and improved the information and controls supporting site delivery.

Scope of responsibility and evidence

Approximately 30 changes were progressed through action close-out. Some remained open at the recorded review point.

Tools and methods

  • Engineering Management of Change
  • Historian
  • P&ID review
  • RAMS
  • Causal-tree investigation
  • Work coordination