Engineering change and site operations
Progressed engineering-change actions across Motherwell and Grangemouth and chaired monthly reviews for six months. Coordinated technical, contractor and documentation actions alongside improvements to operating information and site controls.
Engineering project index
Used regular change reviews to coordinate technical actions and dependencies, supported by site information and contractor-control checks.
Objective and context
Progress controlled engineering change within live air-separation operations. Technical actions, contractor controls, equipment interfaces and documentation needed to remain aligned through delivery and close-out.
Technical contribution
Change coordination
Progressed actions across approximately 30 engineering changes and chaired monthly reviews for six months. Workstreams included equipment interfaces, cooling towers, cryogenic vessel service changes and pump insulation.
Technical and contractor actions
Coordinated technical, contractor and documentation actions, including RAMS, P&ID updates and written-scheme actions. Checked turnaround contractor controls and supported a causal-tree investigation into contractor RAMS non-compliance.
Operating information
Improved Historian mimics with site and remote-operations teams and analysed process-safety indicator trends. Connected process information with a clearer view of plant operation.
Work coordination
Developed a Work Assignment Tool with the plant manager to support the allocation and coordination of site work.
Results and scope
Progressed engineering-change actions across two operating sites, maintained a regular review process and improved the information and controls supporting site delivery.
Approximately 30 changes were progressed through action close-out. Some remained open at the recorded review point.